When to Hire a Smart Home Integrator
Building a custom home in Collingwood or The Blue Mountains means hundreds of decisions. Most of them can wait. A few cannot, and the technology ones catch people off guard.
The short answer is this: bring a smart home integrator in while the architect is still drawing. Here is why, and what you need to decide at each stage of the build.
Why earlier is easier
Your builder schedules trades in a set order. Footings, framing, rough-in, insulation, drywall, paint, then finishes. Wire goes in the walls during rough-in. Once drywall goes up, adding a wire means cutting into a finished wall.
The Town of Collingwood's building inspections show the order clearly. Insulation and vapour barrier get inspected before drywall and finishes go on. For anything that lives inside a wall, that inspection is the practical deadline.
So the real question is not when you want the system. It is when the decisions that shape the walls get made.
Stage one: while the architect draws
This is the stage most owners skip, and it matters most. A few choices here change the drawings themselves:
- Where the equipment room goes, how big it is, and how it stays cool.
- Which rooms get music, TVs, or a theatre.
- Which lighting control system you want, since it changes the switch plan.
- Whether motorized shades will sit in recessed pockets in the ceiling.
- Where cameras, the alarm panel, and wireless access points belong.
None of this needs a final budget yet. It needs a plan on paper. Our pre-construction consulting is built for this stage, and we sit with your architect and builder while the design comes together.
Stage two: during framing
Once the walls are up, the plan becomes real. Framing is when you add what is hard to add later:
- Solid backing in the wall behind every TV.
- Shade pockets framed into the ceiling.
- Conduit between floors, to the garage, and out to the dock or patio.
- Room in the ceiling for speakers, away from joists and ducts.
Walk the framed house with your smart home integrator and your builder together. Most small mistakes show up here, and they are cheap to fix with a pencil.
Stage three: rough-in, before insulation
Rough-in is when the low-voltage wire goes in. Network cable, speaker wire, shade wire, and keypad wire all run back to the equipment room. Back boxes get set at the right height.
This is the window that closes fast. Once insulation goes in, it gets inspected, and drywall follows. Our structured wiring work is planned for this stage, with every run labelled.
Ask for photos of every wall before insulation. They cost nothing now and save guessing later.
Stage four: trim, after paint
After paint, the finish work begins. Keypads, speakers, cameras, and shades go in. The equipment rack is built and tested.
Timing matters here too. Shades and keypads go in after the painters are done, not before. Your integrator should be on the builder's schedule, not squeezed in at the end.
Stage five: before you move in
The last stage is programming and testing. Lighting scenes, audio zones, shades, and security all get set up and checked, room by room.
Then someone should walk your family through every keypad, app, and routine before the keys change hands. You can read how we handle each step in our process.
What deciding late looks like
Starting late does not mean you cannot have a smart home. It means you get fewer choices.
- Cutting and patching finished walls to run new wire.
- Wireless products where a wired one would have been more reliable.
- Keypads where the wire happens to be, not where you want them.
- An equipment room squeezed into a closet that was never meant for it.
If your walls are already closed, there are still good options. Wireless lighting control like Lutron RadioRA 3 was designed for finished homes. It just works best as a plan, not a rescue.
Questions we get
Can you work from my architect's drawings?
Yes. We review the plans, mark up where equipment, wire, and devices go, and coordinate with your builder and electrician before framing starts.
Is it too late if framing is already done?
No. Rough-in has not happened yet, so wire can still go anywhere. Call before insulation goes in.
Do you work on new builds in Thornbury and The Blue Mountains?
Yes. We work across Collingwood, The Blue Mountains, Thornbury, Meaford, Wasaga Beach, Creemore, Craigleith, and Clarksburg.
Do I need to choose every product now?
No. You need to decide what each room will do. Exact products can come later, as long as the wire and space are planned for them.
Get the plan on paper first
A smart home in a custom build starts with drawings, not devices. The earlier the plan exists, the more choices you keep.